LTDS Table 7 Planned Work
Dataset description:
The Long-Term Development Statement (LTDS) provides essential information to assist current and prospective users of National Grid Electricity Distribution’s (NGED) network in identifying...
Source: LTDS Tabular Model
Data Dictionary
| Title | Type | Label | Description | Example |
|---|---|---|---|---|
| Licence | text | Licence area for data |
EMIDS | |
| Grid Supply Point | text | Grid Supply Point |
Chesterfield | |
| Substation or Circuit | text | Substation or Circuit |
Halfway | |
| Planned Work | text | Planned Work |
Upgrade 33/11kV transformers and 11kV switchboard | |
| Impact on Network Capability | text | Impact on Network Capability |
Increase firm capacity & Fault level capability | |
| Status | text | Status |
In Progress | |
| Completion | text | date | 2025 |