LTDS Table 7 Planned Work
Integrate this resource
Access this data via a web API. Further information in the CKAN API guide (opens in new tab).
The Data API can be accessed via the following actions of the CKAN action API.
https://connecteddata.nationalgrid.co.uk/api/3/action/datastore_createhttps://connecteddata.nationalgrid.co.uk/api/3/action/datastore_upserthttps://connecteddata.nationalgrid.co.uk/api/3/action/datastore_searchhttps://connecteddata.nationalgrid.co.uk/api/3/action/datastore_search?resource_id=7d6fbbe5-6774-41e8-810d-1200354afef6&limit=5https://connecteddata.nationalgrid.co.uk/api/3/action/datastore_search?resource_id=7d6fbbe5-6774-41e8-810d-1200354afef6&q=jones
curl -X POST 'https://connecteddata.nationalgrid.co.uk/api/3/action/datastore_search' \
-H "Content-Type: application/json" \
-d '{
"resource_id": "7d6fbbe5-6774-41e8-810d-1200354afef6",
"limit": 5,
"q": "jones"
}'
Data Dictionary
| Column | Type | Label | Description | Example |
|---|---|---|---|---|
| Completion | text | date | Not provided- | 2025 |
| Grid Supply Point | text | Not provided- | Grid Supply Point |
Chesterfield |
| Impact on Network Capability | text | Not provided- | Impact on Network Capability |
Increase firm capacity & Fault level capability |
| Licence | text | Not provided- | Licence area for data |
EMIDS |
| Planned Work | text | Not provided- | Planned Work |
Upgrade 33/11kV transformers and 11kV switchboard |
| Status | text | Not provided- | Status |
In Progress |
| Substation or Circuit | text | Not provided- | Substation or Circuit |
Halfway |