LTDS Table 3 Demand
Dataset description:
The Long-Term Development Statement (LTDS) provides essential information to assist current and prospective users of National Grid Electricity Distribution’s (NGED) network in identifying...
Source: LTDS Tabular Model
Data Dictionary
| Title | Type | Label | Description | Example |
|---|---|---|---|---|
| Licence | text | The name of the licence area from which the data is taken |
EMIDS | |
| GSP Group | text | The name of the substation group that the substation is contained within |
Berkswell 132kV | |
| BSP Group | text | The substation area to which the substation belongs |
Coventry Central | |
| Primary Substation | text | The substation to which the node belongs |
Courtaulds 6.6 | |
| Node | text | Busbar code |
COUR7_BB_1_2 | |
| Status | text | New, Removed or Unchanged |
Unchanged | |
| Operating Voltage | numeric | kV | The voltage at the substation |
6.6 |
| Current Year Max Demand | numeric | MW | The maximum demand seen at the substation between 01/10/2019 to 30/09/2020 |
4.42 |
| Current Year Power Factor | numeric | PF | The Power Factor at the substation |
0.96 |
| Forecast Year 1 | numeric | MW | Forecast Maximum demand year 1. |
4.511 |
| Forecast Year 2 | numeric | MW | Forecast Maximum demand year 2. |
4.614 |
| Forecast Year 3 | numeric | MW | Forecast Maximum demand year 3. |
4.741 |
| Forecast Year 4 | numeric | MW | Forecast Maximum demand year 4. |
4.893 |
| Forecast Year 5 | numeric | MW | Forecast Maximum demand year 5. |
5.072 |
| Firm Capacity of Substation | text | MW | Firm Capacity of the substation site. |
24 |
| Minimum demand Scaling Factor (%) | text | % | Minimum demand scaling factor |
47.56% |