Dispatch Report
Dataset description:
Overview This section of the Flexibility Group focuses on making available regularly produced reports containing procurement and dispatch data. Data The Procurement_Report.csv file...
Source: Flexibility – Reports
Data Dictionary
Title | Type | Label | Description | Example |
---|---|---|---|---|
Tender reference | text | Unique reference of flexibility service tender; where multi-year tender occur, this is shown on multiple lines |
CMZ_T3A_SWE_0005_T3B | |
Incident reference | text | Unique reference of incident for which a service was dispatched |
CMZ_T3A_SWE_0005_2022-10-31 | |
Product | text | Main flexibility product |
Secure | |
Licence area | text | Distribution Licence area |
National Grid Electricity Distribution (South West) Plc | |
Incident location (Grid Supply Point) | text | The area within which a flexibility service was dispatched |
Bridgwater/Street | |
Accepting party | text | Details of the accepting party for dispatched service |
Infinis Limited | |
Flexible Unit Reference | text | Unique ID which links accepted bids to a specific Flexible Unit |
TDSB_T3B_000038 | |
Main technology | text | Main technology used against each tender reference against the G99 of the ECR |
Biofuel - Landfill gas | |
Secondary technology | text | Main technology (where applicable) used against each tender reference against the G99 of the ECR |
||
Constraint Type | text | Pre-fault and post-fault constraint type for which a flexibility service was dispatched |
Post Fault, demand constraint - Restoration | |
Constraint Management Zone Name | text | Unique Constraint Management Zone code |
CMZ_T3A_SWE_0005 | |
Maximum Connection Voltage | numeric | kV | The maximum voltage at which a connection occurs within a CMZ |
33 |
Dispatch capacity (MW) | numeric | MW | The flexible MW dispatched. Average MW for a profiled dispatch. |
0.2 |
Dispatch volume (MWh) | numeric | MWh | The total dispatch energy calculated as Dispatch Capacity x Total Duration |
0.3 |
Dispatch capacity (MVAr) | numeric | MVAr | The flexible MVAr dispatched. Average MVAr for a profiled dispatch. |
0 |
Dispatch volume (MVArh) | numeric | MVArh | The total dispatch energy calculated as Dispatch Capacity x Total Duration |
0 |
Availability Price (Pound/MW/hr) | numeric | Pound/MW/hr | The availability price the flexibility requirement was dispatched at |
125 |
Utilisation Price (Pound/MWh) | numeric | Pound/MWh | The utilisation price the flexibility requirement was dispatched at |
175 |
Service Price (Pound/kW/year) | text | Pound/kW/year | The service price the flexibility requirement was dispatched at |
|
Pricing Strategy | text | Description of pricing strategy associated with pricing. E.g.: fixed, ceiling price, clearing price, adjusted monthly |
FIXED_PRICE | |
Date of instruction (DD/MM/YYYY) | timestamp | Date of dispatch instruction, including notice period |
31/10/2022 | |
Time of instruction (HH:MM) | text | Time of dispatch instruction, including notice period |
16:45 | |
Start date of instruction (DD/MM/YYYY) | timestamp | Start date of dispatch and network need |
31/10/2022 | |
Start time of instruction (HH:MM) | text | Start time of dispatch and network need |
17:00 | |
End date of instruction (DD/MM/YYYY) | timestamp | End date of dispatch and network need |
31/10/2022 | |
End time of instruction (HH:MM) | text | End time of dispatch and network need |
19:00 | |
Actual duration of dispatched utility (HH:MM) | text | Actual duration of service defined within the service windows (dates and times) above |
02:00 | |
Accept time (HH:MM) | text | Actual time a dispatched utility was accepted |
16:45 | |
Notice time (HH:MM) | text | Actual time a notice of the dispatched utility was given |
00:15 | |
Expected duration (HH:MM) (where applicable) | text | Expected duration of a service being dispatched |
02:00 | |
Notes | text | Additional information as required |
||
Dispatch year | text | Reporting year within which dispatch occurred |
2022/23 |